Project Description
Scope of implementation:
-
Cable route with a length of 1,380 m or air HV connection route with a length of 2,130 m from 110 / 22KV PS Poprad-Stráže to the substation at the PP site.
-
Relocation of 22 kV overhead transmission line with a length of 630 meters at the Tatravagónka site.
-
Reconstruction of 22KV protections of transformer cells in 110 / 22KV PS Poprad-Stráže.
-
Complete technological equipment of HV and LV transformer station 22/0.42KV; 2×1, 000KVA at the PP site.
-
Internal site medium and low voltage cable networks
-
Outdoor lighting of the site